B2G/Schedule Roadmap/M2.5
Contents
Objectives
The main focus of Gaia Milestone 2.5 is to have a Developer Preview Phone that increases the audience of developers who can contribute to the overall Boot to Gecko project.
The goal is to land all P1 bugs listed below for the 2.5 milestone as well as the P1 tasks from M2.1.
Timeline
- March 26, 2012 is the drop dead day for M2.5. Here is a break down per day:
Friday 3/23
• Identify final QA checklist for M2.5 acceptance testing
Sunday 3/25
• 11PM PDT All issues for the 2.5 Milestone need to be checked-in and landed in the B2G Repository
• 12AM PDT Cjones tags Final Candidate Build and communicates when ready
Monday 3/26
• 9AM PDT B2G QA test fest to verify all changes that landed in Sunday's build.
• 3PM PDT Meet in Very Good Very Mighty to discuss status
• 11PM PDT All fixes due in B2G Repository
• 12AM PDT Cjones cut *final* build for M2.5
Tuesday 3/27
• 9AM PDT M2.5 Closes Out ===> M3
Projects
Gecko work for the Milestone 2.5
Description | Priority | Status | Details | Owner | i18n | UX Specs | Bugs |
Gecko Updater | P1 | TAKEOFF | details | cjones | |
|
|
Permission DB | P2 | RUNWAY | details | bent/jstraus | |
|
|
Notifications | P1 | RUNWAY | details | TBD | |
|
|
Auto orientation | P1 | INFLIGHT | details | mounir | |
|
|
Prototype Settings API | P2 | INFLIGHT | details | kaze | |
|
|
Network Settings v2 | P1 | INFLIGHT | details | philikon | |
|
|
Device Storage API prototype | P2 | RUNWAY | details | TBD | |
|
|
Gaia work for the Milestone 2.5
Description | Priority | Status | Details | Owner | i18n | UX Specs | Bugs |
Gaia Updater | P1 | INFLIGHT | details | benfrancis | |
|
|
Browser | P1 | INFLIGHT | details | benfrancis | |
|
|
Camera UI | P1 | RUNWAY | details | TBD | |
|
|
P1 | INFLIGHT | details | vingtetun | |
|
| |
Calendar | P2 | INFLIGHT | details | benfrancis | |
|
|
Volume Controls | P1 | INFLIGHT | details | vingtetun | |
|
|
Status Legend:
- RUNWAY - Waiting for design or initial planning
- TAKEOFF - Ready for work to begin
- INFLIGHT - Work is in progress. Patches should be in bugs.
- LANDED - Work has finished and is in the product.
Blockers As of 3/22
Required for M2.5
- Gaia Updater (Fabrice)
- WIFI Issues (Blake/Kaze) <-- needs an issue logged
- App Loading Time (DJF)
- Games GFX Issues (cjones) <-- needs an issue logged
- Hack Auto-Kill for expensive apps (DJF)
QA Milestone Report
M2.5 Release Candidate Testing Focus
- Black box testing of GAIA from a first run approach. Step through each app for functionality, performance, usability
- Since we are tight on time, scope API testing to the functionality GAIA exposes- just stick to app testing
- Verify the list of m2.5blockers
- Verify high value m2.5 changes