This page contains, links, queries and pointer to all information we are using to track the progress on the 1.2 release (Koi).

General

  • Current FirefoxOS roadmap with 1.2 target features.
  • List of whiteboard flags and tagging scheme found here.

User Stories

All Blockers

Blockers per Functional Team

Team Home Page Sprint Page Noms Blockers
Performance Team info Sprint status koi? koi+
Productivity Team info Sprint status koi? koi+
Media Team info Sprint status koi? koi+
Communications Team info Sprint status koi? koi+
Systems Front-End Team info Sprint status koi? whiteboard koi? whiteboard a? koi+ whiteboard koi+
RIL/GPS/CDMA Team info Sprint status koi? koi+
Systems Platform Team info Sprint status koi? whiteboard koi? koi+ whiteboard koi+ combined search combined search w/o 3rd-party keyboard
Device Team info Sprint status koi? koi+

Other Blockers

MetaBug for perf

All Core

Core:DOM, DOM:Apps, DOM:Core & HTML [Owner : Johnny Stenback, Peter Van der Beken]

Core::Canvas:WebGL [Owner : Milan]

Core::DOM:Device Interfaces [Owner : ?]

Core::DOM:Indexed DB [Owner : Jonas Sicking]

Core::Event Handling: [Owner: ? ]

Core::Graphics, Core::Graphics:Layers [Owner: Milan ]

Core::IPC [Owner: Chris Jones ]

Core::Java Script [Owner: Naveed Ihsanullah]

Core::Video/Audio [Owner: CJ Ku?]

Core::Web Audio [Owner: Ehsan Akhgari]

Core::WebRTC [Owner: Randell Jesup, Maire Reavy]

Core::Widget Gonk [Owner: Michael Wu]

Gaia [Owner: Vivien Nicolas]

AudioChannel [Owner Marco]

PDF Viewer [Owner ?]

Gallery [Owner: Hema]

note : This query is included under the media functional team

General [Owner : Relman]

Homescreen [Owner: Gwagner]

Wifi [Owner: Ken Chang]

Builds

NFC [Owner: Ken Chang]

Note : Plugged out entirely of 1.2 based on recent chat with Sandip

Vendcom [Owner: Marco Chen]

Hardware [Owner: Marco Chen]

Localizations [Owner: Axel]

High level Schedule

(I know that release management team is working on a calendar, maybe we can link to that or screenshot something)

Key Milestones

  • End of commitmment planning, Dev start: 6/24
  • 2 week Sprint Cycles (no team is known to be performing 3 week cycles): not all teams will be perfectly aligned with these dates
    • 06/24 - 7/9: Sprint 1
    • 07/10 - 7/25: Sprint 2
    • 07/26 - 8/12: Sprint 3
    • 08/13 - 08/28: Sprint 4
    • 08/29 - 09/16: Sprint 5
    • 09/30 - 10/11: Sprint 6
    • 10/14 - 10/25: Sprint 7
    • 10/28 - 11/8: Sprint 8
    • 11/11 - 11/22: Sprint 9
    • 11/25 - 12/6: Sprint 10

11/28 - 11/29: US Thanksgiving

  • Communicate a soft platform freeze on mozilla-central, for sake of FxOS: 9/6
  • End to end regression testing 1: 9/9 - 9/16
  • Feature Complete - 9/16, partners begin testing
    • Soft string freeze
    • Localization start
    • Partners Begin customization and testing checklists
  • Stakeholder Blocker Scrub: Week of 9/16
    • Regular blocker triage will continue within the Release Management team, to ensure schedule is intact
  • Blocker decisions centralized in Joint Triage: 10/28 - 12/9
    • Stakeholder Blocker Scrub: before we start this
    • End to end regresion testing 2: 10/21 - 10/28
  • Recommended IOT testing start: 10/28
    • Customization testing should be completed by this date
  • Hard string freeze: 11/11
  • Localization complete: 11/25 [? Axel to confirm]
  • Recommended final IOT testing complete: 12/2
  • GM: 12/9
    • GM is the date after which our engineers will only investigate single critical bugs