Firefox for iOS Train Schedule/New Draft

From MozillaWiki
Jump to: navigation, search

Train Schedule - 2017

Version Sprint Start String Freeze/L10N Hand-off Feature Complete QA hand-off QA & L10N App Sign-off Legal Sign-off Submission App Store Content Sign-off Release Release Themes
C***
V8.3?
Aug 14, 2017 Aug 17, 2017 Aug 25, 2017 Aug 25, 2017 Aug 31, 2017
L10N Not Applicable
Aug 31, 2017 Sept 1, 2017 Sept 6, 2017 Sept 7, 2017 TBC
D***
V8.4?
Aug 28, 2017 Aug 31, 2017 Sept 8, 2017 Sept 8, 2017 Sept 14, 2017
L10N Not Applicable
Sept 14, 2017 Sept 15, 2017 Sept 20, 2017 Sept 21, 2017 TBC
E***
V9.0
Sept 11, 2017 Sept 14, 2017 Sept 22, 2017 Sept 22, 2017 Sept 28, 2017 Sept 28, 2017 Sept 29, 2017 Oct 4, 2017 Oct 5, 2017 TBC
F***
V9.1
Sept 25, 2017 Sept 28, 2017 Oct 6, 2017 Oct 6, 2017 Oct 12, 2017 Oct 12, 2017 Oct 13, 2017 Oct 18, 2017 Oct 19, 2017 TBC
G*** Oct 9, 2017 Oct 12, 2017 Oct 20, 2017 Oct 20, 2017 Oct 26, 2017 Oct 26, 2017 Oct 27, 2017 Nov 1, 2017 Nov 2, 2017 TBC
H*** Oct 23, 2017 Oct 26, 2017 Nov 3, 2017 Nov 3, 2017 Nov 9, 2017 Nov 9, 2017 Nov 10, 2017 Nov 15, 2017 Nov 16, 2017 TBC
I*** Nov 6, 2017 Nov 9, 2017 Nov 17, 2017 Nov 17, 2017 Nov 23, 2017 Nov 23, 2017 Nov 24, 2017 Nov 29, 2017 Nov 30, 2017 TBC
J*** Nov 20, 2017 Nov 23, 2017 Dec 1, 2017 Dec 1, 2017 Dec 7, 2017 Dec 7, 2017 Dec 8, 2017 Dec 13, 2017 Dec 14, 2017 TBC
K*** Dec 4, 2017 Dec 7, 2017 Dec 15, 2017 Dec 15, 2017 Dec 21, 2017 Dec 21, 2017 Dec 22, 2017 TBC TBC TBC

Legend of Milestones

  • Sprint Start - Development work kicks off based on priorities identified, and commitments made in the last planning meeting, and continues for a period of two weeks.
  • String Freeze/L10N Hand-off - All in-app strings for the release have been finalized, landed and vetted by UX/Content Strategy. Engineering generates a string export and provides to L10N by end of day.
  • Feature Complete - Essentially code freeze. All development work on features, and identified bugs is complete as per previously identified priorities/commitments. The only code that should land after this point would be fixes to any issues identified as blockers by QA during their final test run.
  • QA hand-off - A first/potential candidate build is created by Engineering, and passed to QA for final Acceptance Testing. (This is required/performed in addition to the ongoing feature testing which takes place throughout the development cycle, as particular items land.)
  • QA Sign-off - Automated testing, as well as manual feature testing have been completed at a level determined to be sufficient for the release by QA. Any issues identified during acceptance testing, which were deemed to be blockers have been resolved, and the fixes verified by QA.
  • L10N App Sign-off - Currently only for major releases. Strings can be exported for translation on an ongoing basis, but currently do not have the capability to general screenshots for verification on such a quick turn-around
  • Legal Sign-off - Legal is advised of plans at sprint start can decides whether or not further legal review is required for the period/release. If yes, this is the deadline by which all review has been completed, and any issued addressed to legal team's satisfaction.
  • Submission - All content in 'locked' fields on the app store has been finalized, signed off and posted. Release candidate build is uploaded, and submitted for review.
  • App Store Content Sign-off - All content, including any 'unlocked' fields has been finalized, signed off and posted.
  • Release - Application has been approved, and set is now set to 'Ready for Sale'.