Air Mozilla/Weekly-Status-Reports/2012-03-14

From MozillaWiki
Jump to: navigation, search
Summary
DOC VERSION: 1.0 STATUS REPORT AS OF: March 14, 2012
AUTHOR: Benjamin Sternthal
TPM: Benjamin Sternthal
PROJECT SPONSOR: Richard Milewski
PROJECT WIKI: Air_Mozilla
Status
1. STATUS
Status Item On Track Caution Crisis N/A Comment
OVERALL STATUS X
Schedule X
Scope X
Budget X
Schedule & Budget
2. SCHEDULE
Start Date Completion Date
Original Current Original Current
2011-12-22 2011-12-22 R1 2012-04-16 N/A
3. BUDGET
Original Current
Cost Of Work
Performed
Estimated
Actual Cost
Variance
at
Completion
N/A N/A N/A N/A
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS
  • Q1 Scope Meeting With MRZ/Zander etc.
    • Decided upon Q1 scope, theme refresh based on mozilla for Moz Camp BA (april 20)
  • Met with webdev confirmed Q1 scope/dates
  • Checking On QA/Sec Reqs - Bugs Filed
Upcoming Tasks
5. UPCOMING TASKS
Task Owner Due Date Bugzilla Comments
R1 Milestone Schedule & Approve BS/Team -- In Progress
R1 Create Any Housekeeping Bugs (QA/IT) BS -- In Progress
R2 Develop Use Cases For Fred RM 2012-03-07 -- Complete
R2 Identify Systems / Scope FW/BS/RM 2012-03-14 -- In Progress
Final Design TS 2012-03-12 --- In progress
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new)
Issue Description Owner Priority Date Due Bugzilla Status
Confirm New Dates/Timeline is OK RM high 2012-02-22 -- Complete
Digital Asset Manager Use/Not Use For R2 RM high -- --
Project Milestones
7. PROJECT MILESTONES
Issue Owner Target
Completion
Date
Revised
Completion
Date
Acutal
Completion
Date
Bugzilla Status
Design
   R2 Design Approved TS 3/12
   R2 PSD Delivered TS 3/16
WebDev
   R1 Coding CC 3/26 - 4/6
   R1 Design Review TS/CC
   R1 Live CC 4/16
Content
   R1 Content Entry RM
Privacy
   R1 Review Stacy
QA
   R1 Review SD 735459
Security
   R1 Review TBD 735454
IT
   R1 Setup Staging MZ Soon
   R1 Launch Plan CC/MZ