Air Mozilla/Weekly-Status-Reports/2012-03-21
From MozillaWiki
Contents
Summary
DOC VERSION: 1.0 | STATUS REPORT AS OF: March 21, 2012 |
AUTHOR: Benjamin Sternthal |
TPM: Benjamin Sternthal |
PROJECT SPONSOR: Richard Milewski |
PROJECT WIKI: Air_Mozilla |
Status
1. STATUS | |||||
Status Item | On Track | Caution | Crisis | N/A | Comment |
OVERALL STATUS | X | ||||
Schedule | X | ||||
Scope | X | ||||
Budget | X |
Schedule & Budget
2. SCHEDULE | |||
Start Date | Completion Date | ||
Original | Current | Original | Current |
2011-12-22 | 2011-12-22 | R1 2012-04-16 | N/A |
3. BUDGET | |||
Original | Current Cost Of Work Performed |
Estimated Actual Cost |
Variance at Completion |
N/A | N/A | N/A | N/A |
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS |
|
Upcoming Tasks
5. UPCOMING TASKS | ||||
Task | Owner | Due Date | Bugzilla | Comments |
R1 Milestone Schedule & Approve | BS/Team | -- | -- | Complete |
R1 Create Any Housekeeping Bugs (QA/IT) | BS | -- | -- | Complete |
R2 Identify Systems / Scope | TBD | 2012-03-14 | -- | On Hold |
R2 Final Design | TS | TBD | --- | On Hold |
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new) | |||||||
Issue Description | Owner | Priority | Date Due | Bugzilla | Status | ||
Confirm New Dates/Timeline is OK | RM | high | 2012-02-22 | -- | Complete | ||
Digital Asset Manager Use/Not Use For R2 | RM | high | -- | -- |
Project Milestones
7. PROJECT MILESTONES | |||||||
Issue | Owner | Target Completion Date |
Revised Completion Date |
Acutal Completion Date |
Bugzilla | Status | |
Design | |||||||
R2 Design Approved | TS | 3/12 | On Hold | ||||
R2 PSD Delivered | TS | 3/16 | On Hold | ||||
WebDev | |||||||
R1 Coding | CC | 3/26 - 4/6 | |||||
R1 Design Review | TS/CC | 4/2 - 4/6 | |||||
R1 Live | CC | 4/16 | |||||
Content | |||||||
R1 Content Entry | RM | 4/5 - 4/10 | |||||
Privacy | |||||||
R1 Review | Stacy | N/A | |||||
QA | |||||||
R1 Review | SD | 735459 | Confirming If Necessary | ||||
Security | |||||||
R1 Review | TBD | 735454 | Confirming If Necessary | ||||
IT | |||||||
R1 Setup Staging | MZ | N/A Already Exists | |||||
R1 Launch Plan | CC/MZ | 4/06 |