Betafarm/Weekly-Status-Reports/2012-02-21

From MozillaWiki
Jump to: navigation, search
Summary
DOC VERSION: 1.0 STATUS REPORT AS OF: Feb 21 2012
AUTHOR: Benjamin Sternthal
TPM: Benjamin Sternthal
PROJECT SPONSOR: David Ascher
PROJECT WIKI: Betafarm
Status
1. STATUS
Status Item On Track Caution Crisis N/A Comment
OVERALL STATUS X
Schedule X
Scope X
Budget X
Schedule & Budget
2. SCHEDULE
Start Date Completion Date
Original Current Original Current
Jan 17 Jan 17 March 30 N/A
3. BUDGET
Original Current
Cost Of Work
Performed
Estimated
Actual Cost
Variance
at
Completion
N/A N/A N/A N/A
Recent Accomplishments
4. RECENT ACCOMPLISHMENTS
  • Had weekly meeting, ben is now TPM
  • Had scope & milestone meeting for Q1 release
Upcoming Tasks
5. UPCOMING TASKS
Task Owner Due Date Bugzilla Comments
Define Scope Q1 Release DA/BS 2012-02-20 Complete
Create Any Housekeeping Bugs (QA/IT) BS 2012-02-21 In Progress
Schedule Sign Off By Teams BS/Teams 2012-02-24 ---
Major Issues
6. MAJOR ISSUES, CONCERNS & IMPACTS (* = new)
Issue Description Owner Priority Date Due Bugzilla Status
Decide on Branding & Domain Name * DA High 2012-03-01 --
HP Design * DA High 2012-03-07 728410
Project Milestones
7. PROJECT MILESTONES
Issue Owner Target
Completion
Date
Revised
Completion
Date
Actual
Completion
Date
Bugzilla Status
WebDev
  Release 1 Ready To Test PM/Tofu 3/16
  Release 1 Live PM/Tofu 3/30
Content
  
Privacy
  
Security
  
QA
  
IT