Agenda:

  • Follow ups from last week:
    • mrz will add HA testing to the qa checklist (what happens when we lose a cable etc)
    • We need to triage add-on reviews. Ragavan and Justin to work on that.
      • Status: Don't have a plan yet.
    • We need a support plan. Ragavan and Tenser to work on that.
      • Status: Tenser and Ragavan met and are working on a plan for getting SUMO KBs in place.
    • Figure out if we can make string changes to the name for 1.3 or if we will need a 1.4.
      • Status: Done. We'll call 1.3 Firefox Sync.
    • Release checklist from Matt.
  • Updates:
    • Client
      • 1.3b1
      • Code complete by Apr 30
      • UI/UX work
      • l10n
    • Sync server
    • Registration server
    • QA
      • Client:
        • Weave1.3b1 Testday went well. (12 bugs filed, 3 already fixed in 1.3b2)
        • Currently executing the 1.3 client test plan against 1.3b2
      • Load:
        • Load Testplan here.
        • Includes Release checklist. Will be sent out after meeting for review.
        • Working on a modified testplan for uTest to follow during load testing week
      • Thick client automation (jgriffin)
        • Python testrunner work completed. Can now run end to end user created tests to test bookmark sync
        • Overview and builds are up.
        • captcha bug 560364 fixed, thanks zandr
        • next week: extension code to allow tests for other syncs (passwords, history, tabs, etc.)
    • Ops
    • iPhone client
    • Release schedule
      • Code freeze (for blockers): Apr 30
      • Registration server code complete: Need date from Les
      • String Freeze: Apr 30
      • H/W set up complete and configured: May 5
      • Load testing done : May 13
      • l10n complete: May 11
      • Security reviews done: May 10
      • RC release date: May 12
      • QA release sign off: May 13
      • Unit tests for Primary done: May 10
      • Web content finalized and staged: May 13
      • PR/Announcement complete and finalized: May 13
      • GA date: May 17, 2010


Notes:

  • mrz has added to the checklist, racking being done now, may be a day ahead.
  • Matt is going to require some feedback his checklist, will send email out today.
  • 1.3b1 was a first cut at addressing usability issues. More iterations to come on the first and last screens. Should be wrapped by end of this week.
  • Had to do an early 1.3b2 (along with 1.2.2) to address trunk breakage.
  • Plan is to release 1.3b3 by end of this week, with no blockers (feature, ui and string freeze)
  • Client gut check feels like it's on track says mconnor.
  • l10n is blocking on string freeze.
  • Sync server is code complete for 1.3 launch. Migrations are done per user.
  • memcache is in stage and will be load tested against production.
  • quotas can be tested against stage.
  • security reviews for sync server will start and have it done by next week.
  • les needs some reviews on his registration patch, unsure how aravind's acl changes affect him.
  • toby/les/clyon to sync up and will get a date.
  • See updates above. Test day got 12 bugs, 3 already fixed.
  • Thick client testing is not 1.3 blocker.
  • uTest contracts are in legal review.
  • May 17 production migration checklist (owner: zandr)
  • Marketing plan is going to be slowly ramped up, so we can dial up/down based on feedback. Also expecting the iPhone client to help get users.
  • iPhone client project page: https://intranet.mozilla.org/Mobile/iPhoneWeaveClient1.0