Firefox Activity Stream Program - Cross-Platform Status Report - Feb-06-2017
Overall Project Health
On track, issues well managed Some risks, unknowns without clear mitigations Blocked on deliverables, needs decision, escalation required
Platform/Area | Version | Health | Notes |
---|---|---|---|
Desktop | FF55 | MVP Scope solidified and broken down. MVP delivery schedule created, and being managed to. 'Sirmilik' sprint was kicked off Feb 6th, ending Feb 19th . | |
Android | FF54 | Sprint 1.15 (ending Feb 19) has been kicked off. MVP feature set somewhat at risk for FF54 and will be monitored. Team sprint capacity tracking lower for last two sprints, but has moved back upwards. | |
iOS | V8.0 | Sprint 1.15 (ending Feb 19) has been kicked off and V7.0 development period is in progress. MVP feature development still on track for V8.0, but recent lower sprint capacity numbers may impact available time to test. Continuing to monitor. |
Exec Summary/Hot Topics
General
- Engineering breakdown of MVP user stories and forecasting completed for ALL Platforms!
- Q1 OKRs have been drafted and reviewed for all teams.
- Desktop sprint cadence was adjusted in January, so sprint timing has been synchronized for all platforms.
Desktop
- Current Sprint 'Sirmilik'
- MVP breakdown work and MVP delivery forecast completed.
- Original forecast had all MVP features, and Graduation work landed by FF56, but investigating uplift of final FF56 deliverables to FF55.
- Upon completion of most recent sprint(Riding Mountain), capacity numbers increased (23 -> 24). If the current pace is maintained the team would be on track to meet the FF55 merge, and the uplift scenario would not be necessary.
Android
- Current Sprint 1.15
- Continuing on with remaining MVP feature development. MVP Backlog can be found here.
- Somewhat at risk for FF54. Capacity numbers decreased in January but are rebounding. Monitoring.
iOS
- Current Sprint 1.15
- Continuing on with remaining MVP feature development. MVP Backlog can be found here.
- Development on track for V8.0, but decreased capacity numbers in January take away available time to test, increasing risk. Monitoring.
Risks & Issues
Description of Risk/Issue | Affected Platform(s) | State | Owner | Version | Plan to Resolve/Mitigation | Target Date |
---|---|---|---|---|---|---|
Team work capacities & therefore MVP delivery date unknown | All | CLOSED | Jenn | TBD | MVP Breakdown and Forecasting completed for all platforms. | Feb 6th |
Team sprint capacities decreased | iOS & Android | Open | Eng | FF54 and V8.0 | Numbers for both iOS and Android teams dropped in January, but did rebound somewhat in sprint 1.14. Numbers will continue to be monitored and reported. | |
Development Status
On track, issues well managed Some risks, unknowns without clear mitigations Blocked on deliverables, needs decision, escalation required
For more details please visit:
- Desktop Activity Stream Trello Board
- Android Activity Stream Trello Board
- iOS Activity Stream Trello Board
Please see the following for detailed development state (bug level):
- Desktop MVP Project on GitHub
- Mobile Sprint Planning - iOS & Android - Shows both current sprint, and MVP backlog remaining
- Mobile Performance - work completed to date for both iOS & Android