Firefox/Activity Stream/Status/12-Jan-2017

From MozillaWiki
Jump to: navigation, search

Firefox Activity Stream Program - Cross-Platform Status Report - Jan-12-2017

Overall Project Health

Green-sm.jpg On track, issues well managed Yellow-sm.jpg Some risks, unknowns without clear mitigations Red-sm.jpg Blocked on deliverables, needs decision, escalation required

Platform/Area Version Health Notes
Desktop TBC

Yellow-sm.jpg

Yellow status due to the fact that final MVP breakdown work and schedule is still pending. Shield study is complete and report of findings will be distributed soon. Work week next week (Jan 16-20).
Android FF54

Green-sm.jpg

Currently in sprint 1.13 (ending Jan 22). MVP feature set on track for FF54.
iOS V8.0

Green-sm.jpg

Currently in sprint 1.13 (ending Jan 22) and V7.0 development period is in progress. MVP feature set on track for V8.0.

Exec Summary/Hot Topics

General

  • Engineering breakdown of MVP user stories is complete for both mobile platforms, and forecasting completed.
  • Desktop work week happening Jan 16-20 to complete MVP breakdown, discuss any changes necessary based on finding from Shield study, finalize forecasting, define work required for TestPilot graduation, and also define Q1 OKRs.


Desktop

  • Current Sprint 'Quttinirpaaq'
  • Planning to complete MVP breakdown work and MVP delivery forecast in January (16-20).
  • Discussions have begun on how to 'graduate' AS code to the trains, vs the current add-on. More in depth discussion planned for January work week.
  • Shield study completed. Summary reported of findings will be distributed soon. Feature changes based on findings will be defined during the work week next week.

Android

  • Current Sprint 1.13
  • Breakdown and forecasting complete.
  • Continuing on with remaining MVP feature development. MVP Backlog can be found here.
  • On track for FF54

iOS

  • Current Sprint 1.13
  • Breakdown and forecasting complete.
  • Continuing on with remaining MVP feature development. MVP Backlog can be found here.
  • On track for V8.0

Risks & Issues

Description of Risk/Issue Affected Platform(s) State Owner Version Plan to Resolve/Mitigation Target Date
Team work capacities & therefore MVP delivery date unknown All Open Jenn TBD Closed for mobile, but still open for Desktop. Will be addressed and resolved during January work week. Jan 20th

Development Status

Green-sm.jpg On track, issues well managed Yellow-sm.jpg Some risks, unknowns without clear mitigations Red-sm.jpg Blocked on deliverables, needs decision, escalation required

For more details please visit the Activity Stream Trello Board

MVP Feature Development

Feature Description Platform(s) Meta Bug Health Status

Green-sm.jpg

Green-sm.jpg

Green-sm.jpg

Green-sm.jpg

Green-sm.jpg

Important Links/References