Firefox/Activity Stream/Status/21-Mar-2017
From MozillaWiki
< Firefox | Activity Stream | Status
Firefox Activity Stream Program - Cross-Platform Status Report - Mar-21-2017
Overall Project Health
On track, issues well managed Some risks, unknowns without clear mitigations Blocked on deliverables, needs decision, escalation required
Platform/Area | Version | Health | Notes |
---|---|---|---|
Desktop | TBC - Re-baselining | MVP feature development progressing well. 'Vuntut' sprint was kicked off Mar 20th, ending Apr 2nd . Revised Graduation plans nearly finalized and broken down. Aiming to complete this exercise and produce new schedule by end of week. | |
Android | FF?? | Sprint 1.18 (ending Apr 2) has been kicked off. Team capacity impacted by ~66% as resources temporarily assigned to another higher priority initiative. Schedule will be re-baselined once all resources are back on board. | |
iOS | V8.0 | Sprint 1.18 (ending Apr 2) has been kicked off; final sprint for V8.0 feature development. MVP feature development on track for V8.0. |
Exec Summary/Hot Topics
Desktop
- Current Sprint 'Vuntut
- Graduation plans are being revisited. Instead of landing entirely as a system add-on, investigating breaking into various modules, and landing majority of code directly in Nightly. Investigation & Breakdown work is nearing complettion, and re-baseline of schedule aiming to complete by the end of the week.
Android
- Current Sprint 1.18
- Continuing on with remaining MVP feature development. MVP Backlog can be found here.
- Schedule will need to re-baselined once all resources are back in place. 2/3 of team has been reassigned temporarily to another high-priority initiative.
iOS
- Current Sprint 1.18
- Continuing on with remaining MVP feature development. MVP Backlog can be found here.
- Development on track for V8.0
Risks & Issues
Description of Risk/Issue | Affected Platform(s) | State | Owner | Version | Plan to Resolve/Mitigation | Target Date |
---|---|---|---|---|---|---|
Team sprint capacities decreased | iOS & Android | Open | Eng | FF54 and V8.0 | Numbers for both iOS and Android teams dropped in January, but did rebound somewhat in sprint 1.14. Numbers will continue to be monitored and reported. | |
Android AS resource availability | Android | Open | Eng | 2/3 Android resources temporarily reassigned. | Mar 31 | |
Development Status
On track, issues well managed Some risks, unknowns without clear mitigations Blocked on deliverables, needs decision, escalation required
For more details please visit:
- Desktop Activity Stream Trello Board
- Android Activity Stream Trello Board
- iOS Activity Stream Trello Board
Please see the following for detailed development state (bug level):
- Desktop MVP Project on GitHub
- Mobile Sprint Planning - iOS & Android - Shows both current sprint, and MVP backlog remaining
- Mobile Performance - work completed to date for both iOS & Android