Firefox Activity Stream Program - Cross-Platform Status Report - Nov-28-2016
Overall Project Health
On track, issues well managed Some risks, unknowns without clear mitigations Blocked on deliverables, needs decision, escalation required
Platform/Area | Version | Health | Notes |
---|---|---|---|
Desktop | Add-On | 'Okanagan Lake' sprint in progress, with end date of Dec 4th. Yellow status due to the fact that final MVP breakdown work and schedule is still pending. Shield study in progress. AS 'Graduation' planning/discussions underway. | |
Android | FF52 TBC | Currently in sprint 2.0 (ending Dec 11). Currently not confirmed if 52 is the delivery vehicle as final MVP breakdown, and subsequent forecasting is still underway (hence Yellow status), targeting to complete this sprint. | |
iOS | V7.0 TBC | Currently in sprint 2.0 (ending Dec 11) and V7.0 development period has begun. V7.0 as the AS delivery vehicle is not yet confirmed as final MVP breakdown, and subsequent forecasting is still underway (hence Yellow status), targeting to complete this sprint. |
Exec Summary/Hot Topics
General
- Engineering breakdown of MVP user stories is not yet complete for all platforms. All teams are aiming to complete the breakdown exercise in the coming weeks, and once finalized a forecast for delivery of Activity Stream for each platform will be generated and communicated. Mobile platforms are aiming to have a complete schedule by December 9th - status of breakdown mobile completion can be found [1].
Desktop
- Current Sprint 'Mount Revelstoke'
- Planning to complete MVP breakdown work in December to enable creation of MVP delivery forecast.
- Discussions have begun on how to 'graduate' AS code to the trains, vs the current add-on, pending favorable feedback from the Shield study.
Android
- Current Sprint 2.0
- Priorities - finalizing breakdown, tab/home panel, highlights, telemetry.
- Only a handful of breakdowns remain; targeting completion this week (first half of the sprint).
iOS
- Current Sprint 2.0
- Priorities - new tab/home panel, highlights,telemetry
- AS feature development continues through the V7.0 development period (3 sprints ending Jan 8th).
- Only a handful of breakdowns remain; targeting completion this week (first half of the sprint).
Risks & Issues
Description of Risk/Issue | Affected Platform(s) | State | Owner | Version | Plan to Resolve/Mitigation | Target Date |
---|---|---|---|---|---|---|
Final MVP definition still to be solidified | All | Closed | Barbara/Nick | TBD | Product has determined which user stories are considered MVP for all platforms. Team is moving on to finalize engineering breakdown of these stories. | Oct 17th |
Team work capacities & therefore MVP delivery date unknown | All | Open | Jenn | TBD | Dependent on final breakdown of MVP user stories. All teams somewhat delayed due to competing priorities. Mobile nearing completion, Desktop follows by a couple of weeks. | Dec 24th |
Development Status
On track, issues well managed Some risks, unknowns without clear mitigations Blocked on deliverables, needs decision, escalation required
For more details please visit the Activity Stream Trello Board
MVP Feature Development
- This section to be populated upon completion of MVP Definition and Breakdown. In the meantime please see the following for development state details:
- Desktop on GitHub
- Mobile Sprint Planning - work still to complete for current sprint
- Mobile Performance - work completed to date
Feature Description | Platform(s) | Meta Bug | Health | Status |
---|---|---|---|---|
Important Links/References
- Desktop on GitHub
- Mobile Sprint Planning - work still to complete for current sprint
- Mobile Performance - work completed to date