Iteration #4 Status Report

Overall Project Performance

  • From Iterations #1 - #4:
    • Total Story Points Completed: 158
    • Total Features Closed: 35
    • Team Point Velocity: 40 points per iteration
    • Scope Change (Defects and Changes): 77 points over 34 stories
  • Current Backlog Status:
    • Story Backlog: 73 stories ready for upcoming iterations.
    • Legacy Backlog: 0 stories remaining for QA testing.
    • On Hold Backlog: 14 stories remaining for Product Manager clarification before being moved into Story Backlog.
    • Planning Backlog: 4 stories for Team to review, relate to work items and assign point values.
    • Triage Backlog: 5 stories for Team to review, relate to work items and assign point values.

Iteration #4 Performance

  • Highlights
    • Team completed 63 story points over 14 features - a 91% increase in performance from the previous iteration.
    • Team has established a new average velocity rate of 40 story points per iteration - a 25% increase in performance from the previous iteration.
    • Overall performance gain in story points and velocity has resulted in a new production forecast release of February 21, 2014 - a reduction of 60 days (5 iterations) from the previous release update.
    • Review of Triage Backlog resulted in a reduction of outstanding work items from 50 to 4.
    • Implemented Contingency Point Framework which allows us to introduce new scope changes (features, defects and changes) without impacting the production forecast release dates.
    • Metro completed 15 out of the 17 established goals for Q1 - View Goals
  • Story Points
    • Story points committed to: 98
    • Story points completed: 63
    • Completion Rate = 64%
  • Features
    • Features committed to: 19
    • Features completed: 14
    • Completion Rate = 73%
  • Scope Change
    • New Defect Stories: 27 points over 13 stories
    • New Change Stories: 11 points over 5 stories


ID COMPLETED WORK
846365 Change - New window opens in desktop Firefox when closing Metro Firefox
844954 Defect - Devices that only support DX9 fail to startup in Metro mode
851388 Story - Add support for caret selection via touch
831609 Defect - Don't open the home page when launching Metro Firefox for protocol activation, search activation, file activation, and secondary tiles.
850398 Defect - popup notification info bar shows again if "Never For This Site" is selected
849342 Defect - Remember passwords preference does not take effect some times
831614 Story - Set up Sync for both Firefoxes in desktop Firefox
849608 Change - Auto close about, settings, and sync flyout panels on snap view
849699 Defect - Cannot Select Email/Password Text Boxes on Twitter
849604 Defect - Settings list is not populated if opened when program starts
849607 Defect - Sharing in start screen AND if page has no title, should indicate nothing to share instead of error
845155 Story - NewUI - Location Permission info app bar
831923 Story - Use the Firefox Start Top Sites tile group in full screen view
850415 Story - Locate downloaded or saved files using Windows Search


ID INCOMPLETE WORK
848155 Change - Add Colored Bar with Text to Bottom of Topsites Thumbnails
836791 Story - Junior-style back and new tab overlay buttons
831918 Story - Pin, Unpin, Hide, and Restore a Top Site
850737 Story - Smoothly scroll the Firefox Start screen
845484 Story - Choose types of private data to clear in the options flyout


media:IT4_BurnDown_03-27-13.jpg

Forecast Production Schedule

The Expected Production Forecast below is based only on data from Iterations #1 - #4. At the conclusion of each iteration, the production forecast will be updated to reflect the current state of the project. At the conclusion of Iteration #6 there will be enough data to develop the Best Case and Worst Case production forecasts.

Expected Production Forecast

  • Current total project story points: 822
  • Story points completed to date: 158
  • Current Team Velocity: 40
  • Forecasted number of story points remaining to complete the project: 664
  • Forecasted number of iterations remaining to complete the project: 22
  • Forecasted date for completion of development: February 21, 2014


media:Metro_Release_BurnDown_03-27-13.jpg

Iteration Performance History

Iteration #1: View Backlog

  • Story Points
    • Committed = 102
    • Completed = 30
    • Completion Rate = 29%
  • Features
    • Committed = 13
    • Completed = 5
    • Completion Rate = 38%
  • Scope Change
    • New Defects Generated = 0
    • New Changes Generated = 3 points over 1 story


Iteration #2: View Backlog

  • Story Points
    • Committed = 110
    • Completed = 32
    • Completion Rate = 29%
  • Features
    • Committed = 14
    • Completed = 6
    • Completion Rate = 42%
  • Scope Change
    • New Defects Generated = 4 points over 2 stories
    • New Changes Generated = 10 points over 4 stories


Iteration #3: View Backlog

  • Story Points
    • Committed = 69
    • Completed = 33
    • Completion Rate = 47%
  • Features
    • Committed = 14
    • Completed = 10
    • Completion Rate = 71%
  • Scope Change
    • New Defects Generated = 13 points over 6 stories
    • New Changes Generated = 9 points over 3 stories

Upcoming Iteration

  • Firefox Metro Iteration #5
    • Iteration Backlog: View All Work
    • Duration: April 1, 2013 - April 12, 2013
    • New Features: 8.
    • Existing Feature Changes: 5.
    • Existing Feature Defects: 13.