Start of project

  • Name each of the following:
    • Project sponsor: Marketing
    • Main IT contact: oremj
    • Main WebDev contact: aking
    • Main QA contact: TBD
    • Main third party contact (if developed externally): TBD -- we are considering using Social Applications API & will engage a design agency.
    • Final application owner/maintainer: Mary Colvig & Jane Finette
  • Outline the following:
    • Overall goal of the project:
      • Community Action Day/Week will be our first foray into mission-based marketing and aims to differentiate our brand as the competitive landscape heats up.
      • It will aim to inspire our community to take action to improve the Web for others
      • Mozilla will host a platform that will connect volunteers with requests from organizations around the world
      • Our goal is to have over 125,000 volunteer hours
    • Any pre-requisites needed (technology, server capacity, staffing, monitoring, response time, etc)
      • Mozilla will need to create a site that aggregrates volunteer opportunities & local sites.
      • Auto-detect locale for up to 10 languages – remaining locales directed to EN/Global version.
      • Site to offer:
        • Call to action & public goal
        • Volunteer opportunity search by category & location
        • Volunteer opportunity submission
        • Volunteer pledge page name/location/email
        • “LizardFeeder” or similar functionality to share anecdotes & “stories” http://feeds.mozilla.com/
        • Certificate generator similar to Download Day
    • Initial timeline (Contingent on WebDev discussion)
      • CAD Date: in late June (tbd – contingent on WebDev)
      • CAD Launch: 30 days prior
      • Week of March 2: Issue Creative brief
      • Week of April 6: Final artwork
    • External dependencies
      • Local volunteer sites
      • Design agency
      • Copy writer
      • Summer timeframe (need to conduct CAD/W before July)
    • Dev environment specs
      • Stage + Prod env
      • PHP, MySQL, cron + python (lizard feeder)
    • Does this project use any plugins or proprietary technology?
      • No

Complete info on Community Take Action Week

Staging Signoff

In order to get an app into staging, the following should be completed:

  • Code committed to Mozilla source control and tagged
  • Initial architecture review by IT and WebDev
  • Plugin/tech review by Evangelism
  • Site must be password protected
  • Review timeline to go live
  • Review any production requirements so IT can order any new hardware needed

Production Signoff/Launch

  • Final WebDev signoff
  • Final IT signoff
  • Final QA signoff
  • Operations documents filled for support & any training complete
  • Monitors in place