IT/Production Acceptance/Retention
From MozillaWiki
< IT | Production Acceptance
Start of project
Name each of the following:
- Project sponsor: D.Ronitzky
- Main IT contact: Jeremy Orem
- Main WebDev contact: M.Morgan
- Main QA contact: S.Donner
- Main third party contact (if developed externally): AKQA (retention agency); James DeJesus (james.dejesus@akqa.com)
- Final application owner/maintainer: D.Rolnitzky
Overall goal of the project
- Improve Firefox Retention by creating a micro site where users can share a video with friends and family (fightagainstboredom.org). Users will find the micro site through email-to-a-friend, blog posts, facebook, and other outbound media. A Facebook app will be developed (by AKQA) that will allow users to add an "interingness" application to their FB page.
- Updated micro site, FB landing page, and FB app page:
Facebook app:
http://www.facebook.com/apps/application.php?id=6616108785
HTML page with working emailer:
http://www.jamesdejesus.com/ffsite/
Facebook page:
http://www.facebook.com/profile.php?id=6804748403
Any pre-requisites needed (technology, server capacity, staffing, monitoring, response time, etc):
- Goal is to have project up and running by week of 12/24/07
- Domain name "fightagainstboredom.org" purchased -- done
- Access to SVN needed -- done (see bug 403504)
- Staging server required -- done (see bug 408402)
- Urchin analytics needed on micro site -- in progress (bug 408932)
- Email relay information needed for send-to-a-friend functionality -- in progress (bug 408894)
Initial timeline
- Development week of 12/17/07
- Development compelete on 1/2
- Launch sometime around 1/3 or 1/4
External dependencies
- AKQA development time, Mozilla creative signoff and approval, video production, facebook application development
Dev environment specs
- TBD
Staging Signoff
In order to get an app into staging, the following should be completed:
- Code committed to Mozilla source control and tagged: in process
- Initial architecture review by IT and WebDev: date complete?
- Site must be password protected: in process
- Review timeline to go live:
- Review any production requirements so IT can order any new hardware needed: none needed
- Note that AKQA will also be testing all components of the program, including all Facebook components (the application and group page).
Production Signoff/Launch
- Final WebDev signoff
- Final IT signoff
- Final QA signoff -- should use the following QA list as a guideline (http://wiki.mozilla.org/Firefox:Download_Page:Test_Plan)
- Operations documents filled for support & any training complete
- Monitors in place