MDN/Archives/MDNv09x/v095/Demo Studio redesign

From MozillaWiki
< MDN‎ | Archives‎ | MDNv09x‎ | v095
Jump to: navigation, search
Feature Status ETA Owner
Dev Derby challenge page(s) Final testing for 6/7 release 2011-06-07 Retronam
Demo Studio redesign Craig working on templates 2011-06-09 Craig


Notes

  • Rules:
    • Monthly challenges will focus on either:
      • 1 theme with multiple features (mobile demos with touch and orientation)
      • 1 technology/feature (CSS animations)
    • Demos must be submitted before the end of each month to be considered.
    • Any past demos are
  • Judges:
    • Combination of "HTML5 experts" and Mozilla folks (not everyone will vote every month)
    • Panel will be selected for each month's challenge based on theme/technology
  • Voting:
    • Mozilla will determine 3 - 5 finalists for each month
    • Panel will vote on criteria (TBD) and pick the winner
  • Prizes:
    • TBD, but most likely an android device, laptop, etc each month


Next Steps & Open Issues

Next Steps:

Dev Derby (MDN 0.9.5)

  • Identify designer to work on the redesign [DONE: Matt Ternoway to start design work on Monday 5/2]
  • Create wireframes for Matt (jay) [DONE: 5/3]
  • Complete hi-fidelity mockups (matt) [ETA:5/17][DONE: 5/19]
  • Implement pages from mockups (craig) [ETA: 6/1][DONE: 6/1]
  • Get pages onto stage9 with final copy (lorchard) [ETA: 6/3][DONE: 6/3]
  • Test and verify on stage9 (retornam) [ETA: 6/7]

Demo Studio (MDN 0.9.6)

  • Complete hi-fidelity mockups (matt) [ETA: 6/1][DONE: 6/3]
  • Implement pages from mockups (craig) [ETA: 6/9]
  • Get pages on stage9 (lorchard) [ETA: 6/13]
  • Test and verify on stage9 (retornam) [ETA: 6/14]

Open Issues:

  • Finalize themes/technologies for first 3 months of challenges (devengage) [DONE: 5/18]
  • Finalize contest rules, guidelines, judging, etc (stormy) [ETA: 5/19][DONE: 6/1]

Related Bugs & Dependencies

Risks

  • Design needs to be completed by mid-May
    • Dev Derby was completed a bit later on 5/19
    • Demo Studio was reset and scheduled for 0.9.6
  • Tight deadline to launch Dev Derby by June 1
    • Moved Dev Derby to 6/7 release target due to design and copy delays

Designs

Test Plans

Legend (remove if you like)

  Healthy: feature is progressing as expected.
  Blocked: feature is currently blocked.
  At Risk: feature is at risk of missing its targeted release.
ETA Estimated date for completion of the current feature task. Overall ETA for the feature is the product release date.