Status Report for Firefox on iOS for the period of 09/09/2015 - 16/09/2015

Overall Project Health

This Week Last Week

YELLOW.jpg

YELLOW.jpg

Exec Summary/Hot Topics

  • V1.0 has now been made available in Canada.
  • V1.1 estimation of initial scope breakdown was completed, but still some additional clarification/breakdown trickling in.
  • Schedule for V1.1 available (see mana link at the end of this report)
  • V1.1 Build#2 will be made available internally, and will also be the first build to release externally via TestFlight
    • String freeze is THIS FRIDAY September 18th
    • Scope is being monitored and managed aggressively. Any 'nice-to-have' features that do not have strings available for the 18th will be cut from the list.
    • 'FxA Sign-up From Device' is considered 'At Risk'. Required resources are unavailable currently due to other priority work assignments.

Risks & Issues

Description of Risk/Issue State Owner Plan to Resolve/Mitigation Target Date
Resourcing constraints OPEN - Monitor Jenn/Eng Mgt The team is smaller by 1.5 full-time, plus 1 intern, compared to V1.0 resourcing over the past few months. Scope and resource allocation must be monitored closely. Currently affecting feature development for 'FxA Sign-Up From Device'. Ongoing
Timeline constraints OPEN - Monitor Jenn/Eng Mgt Submission target is mid-October to align with campaign target dates, leaving litle development time, to deliver must-have features. No scope creep can be permitted, and progress to be monitored closely. Ongoing

Accomplished for the Last Period

  • V1 launched in Canada
  • Breakdown of V1.1 must-have requirements, and sizing of breakdown outputs
  • V1.0.1 build released to test flight. Will be used as our interim bug-fix release, which is the last until V1.1.
  • First V1.1 build released to internal aurora
  • V1.1 milestone schedule defined and committed to by the team
  • Team continues working toward V1.1 features, particularly focusing on finalizing strings

Planned for Last Period but Not Accomplished

Planned for the Upcoming Period

  • String Freeze 9/18
  • V1.1 Build #2 planned for 9/17
  • Feature development continues

Status Details