Status Report for Fennec - Kinderfox - for the period from 06/08/2015 to 19/08/15
Overall Project Health
This Week | Last Week |
---|---|
Exec Summary/Hot Topics
- Nearly 100% of feature development work completed. Outstanding items as follows:
- Light weight theme: Theme is available. Just code to install pending.
- Additional UI Tests for Restricted Profiles: Basic sanity check test available, but any further automated testing blocked on autophone migration per 1184094
Actions, Risks & Issues
Description of Risk/Issue | State | Owner | Plan to Resolve/Mitigation | Target Date |
---|---|---|---|---|
Project timeline is very short. Delivery of all features for Aug 10 at risk. | CLOSED | All | All major feature development completed per the clarified scope definition | Aug 10 - Completed |
Additional Automated UI Tests for Restricted Profiles | Open | Mobile Eng | Blocked on autophone migration | TBD |
Installation of Kinderfox Lightweight Theme | Open | skaspari | Just the installation of the theme. Theme itself is complete/available | next merge |
Accomplished for the Last Period
- Completed required feature development
Planned for Last Period but Not Accomplished
- N/A
Planned for the Upcoming Period
- Lightweight Theme Installation