Prior Art Revised Project Plan

From MozillaWiki
Jump to: navigation, search

Overview

This is a time line of the remaining tasks to get Prior Art to a stage where it can be shown to outside people.

The schedule should be supported by weekly meetings of the team.

Tasks

1/5/2009 - 1/16/2009

  • Complete user functionality [laura]
    • Administrative role and page bug 461784
    • Remaining parts of basic user functionality [[1]]

2/2/2009 - 2/13/2009

  • Resources [laura]
    • Resources Enhancements: flag as inappropriate, files should be scanned for viruses during upload stage bug 467450

2/2/09 - 2/13/09

  • Revision history for references
    • Revision history for references bug 466005 [aking]
  • Discussion forum per reference
    • Discussion forums for each reference bug 466003 [laura]

2/9/09 - 2/27/09

  • UI polish
    • Polish CSS and layout [neilio]
  • Test and QA
    • Write tests [aking, laura]
    • QA [stephend]

2/23/09 - 3/6/09

  • Test and QA
    • QA [stephend]
  • User acceptance
    • UA testing [Legal]

Optional, if spare time

  • build category administration page (under review) bug 461783