Timelines
We're in the home stretch... scope is fixed and TBG is almost code complete.
Critical Path Timeline
Apr 15th - TBG Staging bugs Fixed
Apr 22nd (1 week approx, 2 weeks would be Apr 29th worse case) Webifyme.allizom.org staged
Apr 25th - WebQA starts
May 6th - WebQA finishes
May 9th - Go / No Go Decision
May 10th - Prod launch
Note
Any slippage in critical path slips prod launch date
Any unaddressed blocker bugs will slip Go / No Go decision
In Parallel Timeline
Apr 24 - May 6th - Infrasec testing (4 days approx)
Apr 22nd - May 6th - Operations builds out prod environment (1 week approx)
Apr 18th - May 6th - L10n Estimate TBD (Apr 15th string freeze)
Triage as needed - TBG, Grace, Krupa, ozten
Apr 15th - May 6th - TBG fixing bugs which have been reported
Operations Notes:
- 2 weeks of work all together (medium risk estimate)
- We'll put app on the Engagement cluster
WebQA
- Estimated 10 days to test
- Asked about Supported browsers
- Will put 15-20 external testers on project
- Load testing? - Not needed unless peak usage estimates are large
- Accessibility - (optional :| ) Marco Zehe and others to test
- NoJS - Need string before string freeze
L10n
- Estimate TBD
- 10 locales?
- Already know about project and some bugs have been filed
InfraSec
- Estimate 4 days
- Once everything works (after WebQA pass starts)
TBG
- Tiffany, Dawn from TBG to join weekly meetings
Next Actions
Grace
[] Stas or Gandalf - L10n time estimates, list of locales
[] Estimate peak and average traffic to the site
[] Estimate conversion rate for people finishing the quiz (image generated)
Stephen
[] Contact Accessibility community for testing
Ozten
[x] Resend https://wiki.mozilla.org/QA/Execution/Web_Testing/Project_Checklist to TBG
[x] Will send email to Gandalf and Stas to ask who will extract strings and setup SVN repo