Webifyme Checkin Apr 13th

Timelines

We're in the home stretch... scope is fixed and TBG is almost code complete.

Critical Path Timeline

Apr 15th - TBG Staging bugs Fixed

Apr 22nd (1 week approx, 2 weeks would be Apr 29th worse case) Webifyme.allizom.org staged

Apr 25th - WebQA starts

May 6th - WebQA finishes

May 9th - Go / No Go Decision

May 10th - Prod launch

Note

Any slippage in critical path slips prod launch date

Any unaddressed blocker bugs will slip Go / No Go decision

In Parallel Timeline

Apr 24 - May 6th - Infrasec testing (4 days approx)

Apr 22nd - May 6th - Operations builds out prod environment (1 week approx)

Apr 18th - May 6th - L10n Estimate TBD (Apr 15th string freeze)

Triage as needed - TBG, Grace, Krupa, ozten

Apr 15th - May 6th - TBG fixing bugs which have been reported

Operations Notes:

  • 2 weeks of work all together (medium risk estimate)
  • We'll put app on the Engagement cluster

WebQA

  • Estimated 10 days to test
  • Asked about Supported browsers
  • Will put 15-20 external testers on project
  • Load testing? - Not needed unless peak usage estimates are large
  • Accessibility - (optional :| ) Marco Zehe and others to test
  • NoJS - Need string before string freeze

L10n

  • Estimate TBD
  • 10 locales?
  • Already know about project and some bugs have been filed

InfraSec

  • Estimate 4 days
  • Once everything works (after WebQA pass starts)

TBG

  • Tiffany, Dawn from TBG to join weekly meetings

Next Actions

Grace

[] Stas or Gandalf - L10n time estimates, list of locales

[] Estimate peak and average traffic to the site

[] Estimate conversion rate for people finishing the quiz (image generated)

Stephen

[] Contact Accessibility community for testing

Ozten

[x] Resend https://wiki.mozilla.org/QA/Execution/Web_Testing/Project_Checklist to TBG

[x] Will send email to Gandalf and Stas to ask who will extract strings and setup SVN repo

Next Meeting

April 20th